August 22, 2009 //
The ceiling is done! There is now drop ceiling through the kitchen and dining areas, lobby and corridors leading away from the lobby.
New lighting fixtures have been installed, tripling the amount of lighting power in each area.
As for the kitchen, the construction crews worked until 7 p.m. Friday. They broke for lunch a few minutes ago with the wall cabinets hung and about 70 percent of the base cabinets installed.
On tap for the day is the installation of the sink, faucet and garbage disposal, new appliances (refrigerator and range; the microwave and exhaust fan are in), pantry cabinet (pictured at the very bottom), the remaining base cabinets and countertop. The crew is confident that everything will be finished today, leaving Monday for cleaning and sanitizing.